Constructed operating exercise / 100-day plan
Sequence the work. Reprice the delay.
to · USD · Proposed capacity and assignments
A feasible first-wave proposal under explicit assumptions. No actual Progress staffing, management approval or completed intervention is represented.
Proposed first-wave decision
Baseline first; validate the temporary cash mechanism before the higher-judgment renewal and service cases. This analyst-authored order demonstrates constrained sequencing, not a company priority decision or optimal schedule.
Constructed proposed plan; no actual assignments, accepted deliverables, management decisions or authorization to execute.
Scheduled acceptance is a forecasting assumption. Actual benefit recognition still requires evidence that the deliverable was accepted and the operating effect occurred.
Cost discipline: All original dated expenses, fees and capex remain unchanged. Benefit suppression is not initiative rejection or cost cancellation. Avoiding or rescheduling a cost requires an explicit separate case revision.
Inspect the original economic assumptions · Review the separate public-company baseline
100-day work and acceptance gates
| Work / accountable role | Start | Finish | Status / dependencies | Required acceptance evidence |
|---|---|---|---|---|
| Reconcile scope and freeze baseline finance foundation | scheduled None Earliest feasible full planning week after prerequisites and release date. | Finance-reviewed tie-out and exclusions; no unresolved material scope mismatch Reviewer: Proposed finance reviewer | ||
| Confirm collectible cohort and terms finance collections-review | scheduled foundation Earliest feasible full planning week after prerequisites and release date. | Aging reconciles to ledger; disputes and credits excluded; no term override Reviewer: Proposed controller | ||
| Review bounded collection action finance collections-gate | scheduled collections-review Earliest feasible full planning week after prerequisites and release date. | Manager reviews cohort, communication, quality stop and original collection dates Reviewer: Proposed company sponsor | ||
| Test enforceability and retention downside commercial pricing-review | scheduled foundation Delayed by recorded capacity conflicts. | Notice dates, caps, channel terms and concessions reconciled; downside retained Reviewer: Proposed finance and commercial reviewers | ||
| Review renewal wave commercial pricing-gate | scheduled pricing-review Earliest feasible full planning week after prerequisites and release date. | Human decision on exact cohort; retention stop and contract notice checks complete Reviewer: Proposed commercial executive | ||
| Evaluate service quality and cost action service service-trial | scheduled foundation Delayed by recorded capacity conflicts. | Safe resolution/reopens assessed; removable cost confirmed separately from freed hours Reviewer: Proposed service and finance reviewers | ||
| Review rollout and vendor commitment service service-gate | scheduled service-trial Earliest feasible full planning week after prerequisites and release date. | Quality threshold, vendor terms, HR/legal implications and rollback owner reviewed Reviewer: Proposed operations executive |
Why Test enforceability and retention downside could not start earlier
| Candidate start | Week | Constraint | Competing work / remaining hours |
|---|---|---|---|
| 3 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 4 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 4 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 |
Why Evaluate service quality and cost action could not start earlier
| Candidate start | Week | Constraint | Competing work / remaining hours |
|---|---|---|---|
| 3 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 4 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 4 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 |
Timing changes the forecast
| Scenario | Original year-one EBITDA | Scheduled year-one EBITDA | EBITDA change | Original day-100 cash | Scheduled day-100 cash |
|---|---|---|---|---|---|
| downside | -327,840 | -327,840 | 0 | -124,000 | -124,000 |
| base | 228,267 | 218,977 | -9,290 | 55,871 | 46,581 |
| upside | 612,976 | 558,397 | -54,579 | 188,626 | 165,980 |
| Scenario / initiative | Original benefit date | Scheduled benefit date | Rule / limitation |
|---|---|---|---|
| downside / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| downside / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| downside / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. |
Valuation remains a multiple sensitivity on year-two recurring contribution, not company fair value. Full monthly, cash and valuation comparisons are in the companion JSON.
Weekly change capacity
Proposed finance lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 20 | 16 | foundation |
| 2 · – | 20 | 16 | foundation |
| 3 · – | 20 | 16 | collections-review |
| 4 · – | 20 | 16 | collections-review |
| 5 · – | 20 | 16 | collections-gate |
| 6 · – | 20 | 16 | collections-gate |
| 7 · – | 20 | 20 | pricing-review, service-trial |
| 8 · – | 20 | 20 | pricing-review, service-trial |
| 9 · – | 20 | 20 | pricing-review, service-trial |
| 10 · – | 20 | 12 | pricing-gate, service-trial |
| 11 · – | 20 | 16 | pricing-gate, service-gate |
| 12 · – | 20 | 8 | service-gate |
| 13 · – | 20 | 8 | service-gate |
| 14 · – | 20 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed data engineer · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 24 | 24 | foundation |
| 2 · – | 24 | 24 | foundation |
| 3 · – | 24 | 8 | collections-review |
| 4 · – | 24 | 8 | collections-review |
| 5 · – | 24 | 8 | collections-gate |
| 6 · – | 24 | 8 | collections-gate |
| 7 · – | 24 | 24 | service-trial |
| 8 · – | 24 | 24 | service-trial |
| 9 · – | 24 | 24 | service-trial |
| 10 · – | 24 | 24 | service-trial |
| 11 · – | 24 | 16 | service-gate |
| 12 · – | 24 | 16 | service-gate |
| 13 · – | 24 | 16 | service-gate |
| 14 · – | 24 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed commercial operations lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 24 | 0 | No planned work |
| 2 · – | 24 | 0 | No planned work |
| 3 · – | 24 | 0 | No planned work |
| 4 · – | 24 | 0 | No planned work |
| 5 · – | 24 | 0 | No planned work |
| 6 · – | 24 | 0 | No planned work |
| 7 · – | 24 | 20 | pricing-review |
| 8 · – | 24 | 20 | pricing-review |
| 9 · – | 24 | 20 | pricing-review |
| 10 · – | 24 | 20 | pricing-gate |
| 11 · – | 24 | 20 | pricing-gate |
| 12 · – | 24 | 0 | No planned work |
| 13 · – | 24 | 0 | No planned work |
| 14 · – | 24 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed service operations lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 20 | 0 | No planned work |
| 2 · – | 20 | 0 | No planned work |
| 3 · – | 20 | 0 | No planned work |
| 4 · – | 20 | 0 | No planned work |
| 5 · – | 20 | 0 | No planned work |
| 6 · – | 20 | 0 | No planned work |
| 7 · – | 20 | 16 | service-trial |
| 8 · – | 20 | 16 | service-trial |
| 9 · – | 20 | 16 | service-trial |
| 10 · – | 20 | 16 | service-trial |
| 11 · – | 20 | 16 | service-gate |
| 12 · – | 20 | 16 | service-gate |
| 13 · – | 20 | 16 | service-gate |
| 14 · – | 20 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Authored priority among dependency-ready tasks; earliest feasible non-preemptive full planning weeks. Seven-day weeks start on the case date; the final two days cannot fit a full-week package. Capacity is net of normal duties. Feasibility is conditional on the inputs, not optimality or observed execution.
Steering and evidence still due
Days 30, 60 and 100 are proposed review checkpoints. Review source exceptions and eligibility; then intervention and quality evidence; then financial variance, attribution and unresolved claims. A failed acceptance gate requires a revised forecast, not a retroactive success claim.
Case history preserves original forecasts and exact-version research reviews separately. Actual assignments, accepted deliverables and financial actuals remain unobserved; the attribution ledger remains implementation work.
Calculation lineage
Plan progress-constructed-100-day-plan · revision capacity-draft-v1
Original underwriting 3dcca88ac16d5713123fde8557567a05ca63201ad66f7a7c5dc13809f0992328
Plan 683dbd498536f0ee37560efc14e1dd5f0abb8efbf150d782f6771f803691a682
Report 25793ad0cfa339032def0ec0bd72f5a01fc50a33cc276fb763dab38f69d8aae7
capacity-schedule/1 · monthly-underwriting/2