Constructed operating exercise / 100-day plan
Sequence the work. Reprice the delay.
to · USD · Proposed capacity and assignments
A feasible first-wave proposal under explicit assumptions. No actual Progress staffing, management approval or completed intervention is represented.
Proposed first-wave decision
Authored allocation stress test using the original resource budgets; extra pricing work must compete for real modeled hours.
Constructed proposed plan; no actual assignments, accepted deliverables, management decisions or authorization to execute.
Scheduled acceptance is a forecasting assumption. Actual benefit recognition still requires evidence that the deliverable was accepted and the operating effect occurred.
Cost discipline: Selected initiatives retain all their dated costs. Explicitly avoidable costs of unselected initiatives are excluded; retained commitments remain once. A blocked selected initiative keeps its costs. No cost is rescheduled by the capacity solver.
Inspect the original economic assumptions · Review the separate public-company baseline
Work excluded from this selection
Only selected initiatives and their required enablers consume modeled capacity. An unselected initiative cannot be an implicit prerequisite. Exclusion does not cancel retained financial commitments.
| Work package | Initiative | Acceptance requirement retained for future selection |
|---|---|---|
| Alternative: Test enforceability and retention downside | pricing-targeted | Notice dates, caps, channel terms and concessions reconciled; downside retained |
| Alternative: Review renewal wave | pricing-targeted | Human decision on exact cohort; retention stop and contract notice checks complete |
One economic pool, explicit choices
Calculation selection: recorded policy. collections-timing; pricing-renewals; service-automation.
Recorded selection: collections-timing; pricing-renewals; service-automation. Retain the original resource budgets: model the first pricing policy on its fixed 60% share and defer the 40% alternative because both work packages do not fit. The deferred share is not reassigned. Service and collections remain separate economic mechanisms.
A calculation override does not amend the recorded policy or authorize work. Save a reviewed case revision to record a different decision.
| Economic pool / rule | Member | Population share | Calculation scope | Owner / rationale / challenge |
|---|---|---|---|---|
| renewal-cohort / partition | pricing-renewals | 60.0% | Selected | Proposed finance and commercial reviewers Authored population budget; customer identity and a company-approved split are unavailable. Overlapping customer populations, unsupported rights or an unapproved intervention design. |
| renewal-cohort / partition | pricing-targeted | 40.0% | Excluded | Proposed finance and commercial reviewers Authored population budget; customer identity and a company-approved split are unavailable. Overlapping customer populations, unsupported rights or an unapproved intervention design. |
| support-vendor-spend / exclusive | service-automation | 100.0% | Selected | Proposed finance and commercial reviewers Authored population budget; customer identity and a company-approved split are unavailable. Overlapping customer populations, unsupported rights or an unapproved intervention design. |
| existing-receivables / exclusive | collections-timing | 100.0% | Selected | Proposed finance and commercial reviewers Authored population budget; customer identity and a company-approved split are unavailable. Overlapping customer populations, unsupported rights or an unapproved intervention design. |
Shares describe authored population scope. They are not probabilities or attribution of realized earnings.
Cost explanation: shared-foundation
Proposed finance and commercial reviewers: Equal explanatory cost shares across four candidates. The full committed posting survives exclusion; no causal attribution. Challenge: Overlapping customer populations, unsupported rights or an unapproved intervention design.
| Date | Owner | Component | Allocated amount |
|---|---|---|---|
| 2026-10-05 | collections-timing | implementation_expense | -6,250.00 |
| 2026-10-05 | pricing-renewals | implementation_expense | -6,250.00 |
| 2026-10-05 | pricing-targeted | implementation_expense | -6,250.00 |
| 2026-10-05 | service-automation | implementation_expense | -6,250.00 |
| 2026-10-05 | collections-timing | operating_cash | -6,250.00 |
| 2026-10-05 | pricing-renewals | operating_cash | -6,250.00 |
| 2026-10-05 | pricing-targeted | operating_cash | -6,250.00 |
| 2026-10-05 | service-automation | operating_cash | -6,250.00 |
100-day work and acceptance gates
| Work / accountable role | Start | Finish | Status / dependencies | Required acceptance evidence |
|---|---|---|---|---|
| Reconcile scope and freeze baseline finance foundation | scheduled None Earliest feasible full planning week after prerequisites and release date. | Finance-reviewed tie-out and exclusions; no unresolved material scope mismatch Reviewer: Proposed finance reviewer | ||
| Confirm collectible cohort and terms finance collections-review | scheduled foundation Earliest feasible full planning week after prerequisites and release date. | Aging reconciles to ledger; disputes and credits excluded; no term override Reviewer: Proposed controller | ||
| Review bounded collection action finance collections-gate | scheduled collections-review Earliest feasible full planning week after prerequisites and release date. | Manager reviews cohort, communication, quality stop and original collection dates Reviewer: Proposed company sponsor | ||
| Test enforceability and retention downside commercial pricing-review | scheduled foundation Delayed by recorded capacity conflicts. | Notice dates, caps, channel terms and concessions reconciled; downside retained Reviewer: Proposed finance and commercial reviewers | ||
| Review renewal wave commercial pricing-gate | scheduled pricing-review Earliest feasible full planning week after prerequisites and release date. | Human decision on exact cohort; retention stop and contract notice checks complete Reviewer: Proposed commercial executive | ||
| Evaluate service quality and cost action service service-trial | scheduled foundation Delayed by recorded capacity conflicts. | Safe resolution/reopens assessed; removable cost confirmed separately from freed hours Reviewer: Proposed service and finance reviewers | ||
| Review rollout and vendor commitment service service-gate | scheduled service-trial Earliest feasible full planning week after prerequisites and release date. | Quality threshold, vendor terms, HR/legal implications and rollback owner reviewed Reviewer: Proposed operations executive |
Why Test enforceability and retention downside could not start earlier
| Candidate start | Week | Constraint | Competing work / remaining hours |
|---|---|---|---|
| 3 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 4 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 4 | resource_capacity: finance | collections-review Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 5 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 | |
| 6 | resource_capacity: finance | collections-gate Remaining 4; requires 16 |
Why Evaluate service quality and cost action could not start earlier
| Candidate start | Week | Constraint | Competing work / remaining hours |
|---|---|---|---|
| 3 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 4 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 4 | resource_capacity: data | collections-review Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 5 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 | |
| 6 | resource_capacity: data | collections-gate Remaining 16; requires 24 |
Timing changes the forecast
| Scenario | Original year-one EBITDA | Scheduled year-one EBITDA | EBITDA change | Original day-100 cash | Scheduled day-100 cash |
|---|---|---|---|---|---|
| downside | -299,504 | -299,504 | 0 | -124,000 | -124,000 |
| base | 130,909 | 121,618 | -9,290 | 55,871 | 46,581 |
| upside | 414,986 | 370,625 | -44,361 | 193,575 | 168,375 |
| Scenario / initiative | Original benefit date | Scheduled benefit date | Rule / limitation |
|---|---|---|---|
| downside / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| downside / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| downside / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. | ||
| downside / pricing-targeted | Unavailable | Excluded by the explicit selection; retained financial commitments remain. | |
| base / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. | ||
| base / pricing-targeted | Unavailable | Excluded by the explicit selection; retained financial commitments remain. | |
| upside / pricing-renewals | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / service-automation | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / collections-timing | Later of original economic assumption and day after scheduled acceptance gate. | ||
| upside / pricing-targeted | Unavailable | Excluded by the explicit selection; retained financial commitments remain. |
Valuation remains a multiple sensitivity on year-two recurring contribution, not company fair value. Full monthly, cash and valuation comparisons are in the companion JSON.
Weekly change capacity
Proposed finance lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 20 | 16 | foundation |
| 2 · – | 20 | 16 | foundation |
| 3 · – | 20 | 16 | collections-review |
| 4 · – | 20 | 16 | collections-review |
| 5 · – | 20 | 16 | collections-gate |
| 6 · – | 20 | 16 | collections-gate |
| 7 · – | 20 | 20 | pricing-review, service-trial |
| 8 · – | 20 | 20 | pricing-review, service-trial |
| 9 · – | 20 | 20 | pricing-review, service-trial |
| 10 · – | 20 | 12 | pricing-gate, service-trial |
| 11 · – | 20 | 16 | pricing-gate, service-gate |
| 12 · – | 20 | 8 | service-gate |
| 13 · – | 20 | 8 | service-gate |
| 14 · – | 20 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed data engineer · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 24 | 24 | foundation |
| 2 · – | 24 | 24 | foundation |
| 3 · – | 24 | 8 | collections-review |
| 4 · – | 24 | 8 | collections-review |
| 5 · – | 24 | 8 | collections-gate |
| 6 · – | 24 | 8 | collections-gate |
| 7 · – | 24 | 24 | service-trial |
| 8 · – | 24 | 24 | service-trial |
| 9 · – | 24 | 24 | service-trial |
| 10 · – | 24 | 24 | service-trial |
| 11 · – | 24 | 16 | service-gate |
| 12 · – | 24 | 16 | service-gate |
| 13 · – | 24 | 16 | service-gate |
| 14 · – | 24 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed commercial operations lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 24 | 0 | No planned work |
| 2 · – | 24 | 0 | No planned work |
| 3 · – | 24 | 0 | No planned work |
| 4 · – | 24 | 0 | No planned work |
| 5 · – | 24 | 0 | No planned work |
| 6 · – | 24 | 0 | No planned work |
| 7 · – | 24 | 20 | pricing-review |
| 8 · – | 24 | 20 | pricing-review |
| 9 · – | 24 | 20 | pricing-review |
| 10 · – | 24 | 20 | pricing-gate |
| 11 · – | 24 | 20 | pricing-gate |
| 12 · – | 24 | 0 | No planned work |
| 13 · – | 24 | 0 | No planned work |
| 14 · – | 24 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Proposed service operations lead · proposed
| Week / period | Net budget hours | Planned hours | Work packages |
|---|---|---|---|
| 1 · – | 20 | 0 | No planned work |
| 2 · – | 20 | 0 | No planned work |
| 3 · – | 20 | 0 | No planned work |
| 4 · – | 20 | 0 | No planned work |
| 5 · – | 20 | 0 | No planned work |
| 6 · – | 20 | 0 | No planned work |
| 7 · – | 20 | 16 | service-trial |
| 8 · – | 20 | 16 | service-trial |
| 9 · – | 20 | 16 | service-trial |
| 10 · – | 20 | 16 | service-trial |
| 11 · – | 20 | 16 | service-gate |
| 12 · – | 20 | 16 | service-gate |
| 13 · – | 20 | 16 | service-gate |
| 14 · – | 20 | 0 | No planned work |
| 15 · – | 0 | 0 | No planned work |
Authored priority among dependency-ready tasks; earliest feasible non-preemptive full planning weeks. Seven-day weeks start on the case date; the final two days cannot fit a full-week package. Capacity is net of normal duties. Feasibility is conditional on the inputs, not optimality or observed execution.
Steering and evidence still due
Days 30, 60 and 100 are proposed review checkpoints. Review source exceptions and eligibility; then intervention and quality evidence; then financial variance, attribution and unresolved claims. A failed acceptance gate requires a revised forecast, not a retroactive success claim.
Case history preserves original forecasts and exact-version research reviews separately. Actual assignments, accepted deliverables and financial actuals remain unobserved; the attribution ledger remains implementation work.
Calculation lineage
Plan allocation-first-wave · revision allocation-partition-proposal
Original underwriting 7eb38c16a006877a8609e4c09a78eb186da0d7bc8cbd2525b81609bdd95c4afb
Plan 3044b673a825e8734d3261c7fe5fb4ee8552af1368e67e654b9b74045a122ae1
Report 0d1e01d4b8e06ba5007354f3075ec5ed9f7ab06f85b5ea54a123d13bf21abe33
capacity-schedule/2 · monthly-underwriting/3